Venasky-Pouru Electric has completed many Trans Canada Pipelines projects within the past years. Some include the following:  

Plant :  Station 58 Ignace Ontario
Prime Contractor: Venasky-Pouru Electric (Direct)
Work Completed:  Plant "B" Complete power and Control change
                                   over.
Year:     1996

Plant :  Station 75 Orient Bay Ontario
Prime Contractor:   Venshore Mechanical 
Work Completed:  New "C" plant and Control Buildings
Year:     1997   

Plant :  Central Communications TCPL,  Thunder Bay Ontario
Prime Contractor:  PCL Constructors Inc.
Work Completed:  Building Wiring, Emergency Generator and
                                   Ups Backup.
Year:     1997

Plant :  Station 62 Upsala Ontario
Prime Contractor :  Venshore Mechanical 
Work Completed:  New "D" Plant complete with  "B","C", and"D" 
                                   Aftercoolers.
Year:     1998

Plant :  Station 58 Ignace
Prime Contractor :  BFC Industrial
Work Completed  :  New "C" Plant and Control Buildings
Year: 1999 

[ Industrial | Commercial | Institutional | Premise Wiring |
Design Build
| Other Services ]



Web Site Design by Venasky-Pouru Electric Limited
Web Site Hosted by Svsystems.Inc
Content ©Copyright 2000